What the official record shows
According to the MoSPI PAIMANA dashboard snapshot for May 2026, Multiple Effect Evaporator at Panipat Refinery and Petrochemical Complex had an original approved cost of ₹165 crore. The record lists cumulative expenditure of ₹178.19 crore. Its revised reported cost was ₹247.69 crore.
The reported revised cost is ₹82.69 crore higher than the original approved cost (50.1%). This numerical difference is not, by itself, evidence of a project overrun or its cause. The originally reported completion date was 30 June 2023; the dashboard lists 30 June 2026 as the revised date. These are officially recorded planning dates, not independently verified evidence that construction was completed on either date.
Project record
| PAIMANA project code | 709783 |
|---|---|
| Sector | Energy & Pipelines |
| Line ministry / department | Ministry of Petroleum and Natural Gas |
| Original approved cost | ₹165 crore |
| Revised cost | ₹247.69 crore |
| Cumulative expenditure | ₹178.19 crore |
| Original end date | 30 June 2023 |
| Revised completion date | 30 June 2026 |
| Reporting period | May 2026 |
MoSPI PAIMANA Public Dashboard ↗
Source: Government of India, Ministry of Statistics and Programme Implementation, PAIMANA Public Dashboard. If the official source has since changed, its current figures may differ from this historical snapshot.