Energy & Pipelines / PAIMANA Project 400012

Kandla–Gorakhpur LPG Pipeline

An official-source project record from the Ministry of Statistics and Programme Implementation. Figures reflect the May 2026 snapshot, not a current progress assessment.

Original approved cost
₹10,088 crore
As reported by PAIMANA
Latest revised cost in snapshot
₹10,088 crore
Not inferred when missing
Cumulative expenditure
₹8,585.71 crore
Reported amount, not completion percentage

What the official record shows

According to the MoSPI PAIMANA dashboard snapshot for May 2026, Kandla–Gorakhpur LPG Pipeline had an original approved cost of ₹10,088 crore. The record lists cumulative expenditure of ₹8,585.71 crore. Its revised reported cost was ₹10,088 crore.

The dashboard records the same original and revised cost. The originally reported completion date was 30 December 2021; the dashboard lists 30 June 2026 as the revised date. These are officially recorded planning dates, not independently verified evidence that construction was completed on either date.

Project record

PAIMANA project code400012
SectorEnergy & Pipelines
Line ministry / departmentMinistry of Petroleum and Natural Gas
Original approved cost₹10,088 crore
Revised cost₹10,088 crore
Cumulative expenditure₹8,585.71 crore
Original end date30 December 2021
Revised completion date30 June 2026
Reporting periodMay 2026
Primary source

MoSPI PAIMANA Public Dashboard ↗

Source: Government of India, Ministry of Statistics and Programme Implementation, PAIMANA Public Dashboard. If the official source has since changed, its current figures may differ from this historical snapshot.