What the official record shows
According to the MoSPI PAIMANA dashboard snapshot for May 2026, Multi Product Pipeline from Irugur to Devangonthi had an original approved cost of ₹678 crore. The record lists cumulative expenditure of ₹1,140.25 crore. Its revised reported cost was ₹1,732 crore.
The reported revised cost is ₹1,054 crore higher than the original approved cost (155.5%). This numerical difference is not, by itself, evidence of a project overrun or its cause. The originally reported completion date was 25 February 2017; the dashboard lists 30 September 2026 as the revised date. These are officially recorded planning dates, not independently verified evidence that construction was completed on either date.
Project record
| PAIMANA project code | 400301 |
|---|---|
| Sector | Energy & Pipelines |
| Line ministry / department | Ministry of Petroleum and Natural Gas |
| Original approved cost | ₹678 crore |
| Revised cost | ₹1,732 crore |
| Cumulative expenditure | ₹1,140.25 crore |
| Original end date | 25 February 2017 |
| Revised completion date | 30 September 2026 |
| Reporting period | May 2026 |
MoSPI PAIMANA Public Dashboard ↗
Source: Government of India, Ministry of Statistics and Programme Implementation, PAIMANA Public Dashboard. If the official source has since changed, its current figures may differ from this historical snapshot.