What the official record shows
According to the MoSPI PAIMANA dashboard snapshot for May 2026, Nimach–Ratlam Doubling (133 km) had an original approved cost of ₹1,096 crore. The record lists cumulative expenditure of ₹1,284.91 crore. Its revised reported cost was ₹1,095.88 crore.
The reported revised cost is ₹0.12 crore lower than the original approved cost (0.0%). This numerical difference is not, by itself, evidence of a project overrun or its cause. The originally reported completion date was 31 October 2027; the dashboard lists 31 October 2027 as the revised date. These are officially recorded planning dates, not independently verified evidence that construction was completed on either date.
Project record
| PAIMANA project code | 705933 |
|---|---|
| Sector | Railways |
| Line ministry / department | Ministry of Railways |
| Original approved cost | ₹1,096 crore |
| Revised cost | ₹1,095.88 crore |
| Cumulative expenditure | ₹1,284.91 crore |
| Original end date | 31 October 2027 |
| Revised completion date | 31 October 2027 |
| Reporting period | May 2026 |