What the official record shows
According to the MoSPI PAIMANA dashboard snapshot for May 2026, Bangalore Suburban Railway Project had an original approved cost of ₹15,767 crore. The record lists cumulative expenditure of ₹3,277.99 crore. A separate revised-cost figure was not reported in the source table.
The dashboard extract does not separately report a revised cost for this record. No revised-cost figure has been inferred. The originally reported completion date was 31 December 2026; the dashboard lists 31 March 2030 as the revised date. These are officially recorded planning dates, not independently verified evidence that construction was completed on either date.
Project record
| PAIMANA project code | 705941 |
|---|---|
| Sector | Railways |
| Line ministry / department | Ministry of Railways |
| Original approved cost | ₹15,767 crore |
| Revised cost | Not separately reported |
| Cumulative expenditure | ₹3,277.99 crore |
| Original end date | 31 December 2026 |
| Revised completion date | 31 March 2030 |
| Reporting period | May 2026 |
MoSPI PAIMANA Public Dashboard ↗
Source: Government of India, Ministry of Statistics and Programme Implementation, PAIMANA Public Dashboard. If the official source has since changed, its current figures may differ from this historical snapshot.