An official-source project record from the Ministry of Statistics and Programme Implementation. Figures reflect the May 2026 snapshot, not a current progress assessment.

Original approved cost
₹1,742 crore
As reported by PAIMANA
Latest revised cost in snapshot
₹2,281.02 crore
Not inferred when missing
Cumulative expenditure
₹924.58 crore
Reported amount, not completion percentage

What the official record shows

According to the MoSPI PAIMANA dashboard snapshot for May 2026, Delhi–Amritsar–Katra Expressway Phase I, Package V had an original approved cost of ₹1,742 crore. The record lists cumulative expenditure of ₹924.58 crore. Its revised reported cost was ₹2,281.02 crore.

The reported revised cost is ₹539.02 crore higher than the original approved cost (30.9%). This numerical difference is not, by itself, evidence of a project overrun or its cause. The originally reported completion date was 22 May 2024; the dashboard lists 30 June 2026 as the revised date. These are officially recorded planning dates, not independently verified evidence that construction was completed on either date.

Project record

PAIMANA project code618486
SectorRoads & Highways
Line ministry / departmentMinistry of Road Transport and Highways
Original approved cost₹1,742 crore
Revised cost₹2,281.02 crore
Cumulative expenditure₹924.58 crore
Original end date22 May 2024
Revised completion date30 June 2026
Reporting periodMay 2026
Primary source

MoSPI PAIMANA Public Dashboard ↗

Source: Government of India, Ministry of Statistics and Programme Implementation, PAIMANA Public Dashboard. If the official source has since changed, its current figures may differ from this historical snapshot.