An official-source project record from the Ministry of Statistics and Programme Implementation. Figures reflect the May 2026 snapshot, not a current progress assessment.

Original approved cost
₹1,307 crore
As reported by PAIMANA
Latest revised cost in snapshot
₹1,578.66 crore
Not inferred when missing
Cumulative expenditure
₹563.2 crore
Reported amount, not completion percentage

What the official record shows

According to the MoSPI PAIMANA dashboard snapshot for May 2026, Delhi–Amritsar–Katra Expressway Phase I, Package IV had an original approved cost of ₹1,307 crore. The record lists cumulative expenditure of ₹563.2 crore. Its revised reported cost was ₹1,578.66 crore.

The reported revised cost is ₹271.66 crore higher than the original approved cost (20.8%). This numerical difference is not, by itself, evidence of a project overrun or its cause. The originally reported completion date was 13 December 2023; the dashboard lists 28 March 2024 as the revised date. These are officially recorded planning dates, not independently verified evidence that construction was completed on either date.

Project record

PAIMANA project code618485
SectorRoads & Highways
Line ministry / departmentMinistry of Road Transport and Highways
Original approved cost₹1,307 crore
Revised cost₹1,578.66 crore
Cumulative expenditure₹563.2 crore
Original end date13 December 2023
Revised completion date28 March 2024
Reporting periodMay 2026
Primary source

MoSPI PAIMANA Public Dashboard ↗

Source: Government of India, Ministry of Statistics and Programme Implementation, PAIMANA Public Dashboard. If the official source has since changed, its current figures may differ from this historical snapshot.