What the official record shows
According to the MoSPI PAIMANA dashboard snapshot for May 2026, Integrated Multi Modal Logistics Hub at Nangal Chaudhary, Haryana — Other Trunk Infrastructure Phase 1 had an original approved cost of ₹763 crore. The record lists cumulative expenditure of ₹430 crore. A separate revised-cost figure was not reported in the source table.
The dashboard extract does not separately report a revised cost for this record. No revised-cost figure has been inferred. The originally reported completion date was 31 December 2023; the dashboard lists 15 May 2028 as the revised date. These are officially recorded planning dates, not independently verified evidence that construction was completed on either date.
Project record
| PAIMANA project code | 707410 |
|---|---|
| Sector | Logistics |
| Line ministry / department | Department for Promotion of Industry and Internal Trade |
| Original approved cost | ₹763 crore |
| Revised cost | Not separately reported |
| Cumulative expenditure | ₹430 crore |
| Original end date | 31 December 2023 |
| Revised completion date | 15 May 2028 |
| Reporting period | May 2026 |
MoSPI PAIMANA Public Dashboard ↗
Source: Government of India, Ministry of Statistics and Programme Implementation, PAIMANA Public Dashboard. If the official source has since changed, its current figures may differ from this historical snapshot.